I began the journal of this project when actual construction of the house began. We were due to dig the hole for the house over Thanksgiving weekend, 1985, but winter set in with a vengeance, and delayed the start until January. As a result, the first entry begins on:

January 20, 1986
Martin Luther King's birthday celebrated -- Dick Wetchensky from Andy's Excavating got out to the lot at about 9:00am. After about an hour, he called for help. The two of them worked the rest of the day. Dirt out of the hole packed onto the future driveway. Warm enough outside to be comfortable with jackets unzipped. They are finished by 6:00pm.
January 21
Cloudy and colder. Rock coming for the driveway. First two trucks get up driveway!(50 foot rise in 100 feet of drive) Third tried to back up the drive and got stuck just below creek crossing. Dumped whole load in 1 pile at bottom of drive. Could not contact last 2 trucks to stop them and began working feverishly with what tools we could muster. Trucks 4 & 5 arrive and leave their loads on top of the one at the bottom. Dick saves the day by showing up with his 'dozer "just to see how we were doing." Forms in the ground for the footings to be poured. Dick smoothed driveway after each concrete truck. Boy, did we get that rock packed in!
January 22
Setting forms for walls today.
January 23
They are pouring walls today. 5 concrete trucks at the site when I arrived. Finished by lunchtime.
January 25
Waterproofing. Weather getting wintry again.
March 21
After a long delay, house drain going in today. Dick back to backfill around walls.
March 22-27
Subfloor work to prepare for basement floor.
March 28 - Good Friday
Poured crawl space floor. Almost half of the floor job done now!
March 29
Trucks will come out on Saturday! Got a crew and began the real basement floor. Rented a power trowel to smooth and polish the floor.
April 7
First purchase of flooring wood. Took most of morning for brother-in-law Bruce to unload by hand.
April 10
Bruce and Stan have been working to place floor joists. Today we begin to nail on tongue- and-groove flooring.
April 12
First floor walls.
April 13
Second-floor joists in over back bedrooms. Cold and rainy.
April 20
Have had lots of rain. Drilling holes in T&G flooring to let puddles drain. Temporary girder over garage going in.
April 21-23
Floor joists. Got Tom Ahart out to install septic tank and field.
April 23-24
Second floor subfloor. Started stairs to top.
big
April 25
Built BIG west wall on upstairs floor. Don't know just yet how we will stand it up. It is 16 feet high at the peak.
April 26
Dad on the truck-mounted electric winch on one side. Stan on the come-along on the other side. Bruce and Mom(98 lbs 5'1") and me(not lots bigger than Mom) to stand up this behemoth. Something seems wrong with this picture. Goes up well until breeze catches it about 6 degrees off perpendicular. Begins to come DOWN. Mom and I are doing our best, guys on the winches sweating this one out. Bruce catches it and the three of us stop the tip. We get it up and braced enough to stay put, and all go down and collapse in relief for 15 minutes. We all thought that one was gone.
April 28
After a day lost to rain, we begin the huge truss that will hold up the floor over the garage. We will have a 24-foot wide garage without a post in the middle, thanks to this big truss. Stan and my uncle, who is an engineer, pulled out calculators and all sorts of books to figure out the engineering of this baby. It will be 10 inches thick, layers of 2X4 trusses and plywood. Those who are not building the truss are sheathing. Something is needed to solidify bracing on the walls. The spring winds keep blowing our tall walls out of plumb, and we have to square everything again and again until we back up our bracing with sheathing.
April 29
Install the garage truss with the help of the electric winch, a big jack, and a lot of hard work. IT IS HEAVY!!
May 3
Most of the upstairs walls are now done. We have enough to start the roof trusses. I am eager to get a roof over all this and quit having so much water on the project. If we had been a professional crew, we would have had this covered by now, but we're doing OK for a crew of 5 who are building this after work. At least Bruce is here full time.
May 5-9
Roof trusses.
May 10
Put up roof trusses and roof sheathing.

May 11 Mother's day
Dinner with Mom & Dad and then put up living room rafters.
May 12-18
Lots of rain slowing wall assembly of loft room. Finally walls up and rafters up.
May 22-24
Roofing and sheathing.
May 26 Memorial Day
Started shingles.
May 31
This has been the wettest spring we have had in a while! So now that we have the roof sheathing on, what do we get? HEAT..... Too hot to work on the roof, so we build the stairs from the basement. Shingled in the evening.
June 1-6
Shingles.
June 7-9
Tuff-R on the walls during the heat of the day. Hope that will keep the insides a little cooler now. Getting ready for windows.
June 10
Windows delivered at 8:30 am. This place is on an east facing hill and is really nice in the mornings! We are going to finally be able to close out some of the animals who have been roaming around leaving telltale signs!
From here, construction required all hands, and I didn't have as much time to write.
First week of June, we get a hint that we may have trouble with our arrangement to get water to the house.
July 6
Huge Rainstorm! Water came roaring down our little creek and came up(6 feet) over our driveway. Washed out the crossing. We also discover the headers over our clerestory windows are not hefty enough to carry the weight of the roof. Roof already on, though. Not a pleasant chapter in this story.

We begin the tedious process of reconstructing the clerestory headers. The headers were made up of 3 layers of 2X8. We jacked up 1 layer, which held up the roof, while we replaced the two others with 2X10's. Then they held the roof up, while the original wood was replaced with larger beams. Luckily, we had enough height to cut the clerestory window holes 2 inches lower. A setback, but not a show stopper.
We also form and pour a retaining wall on the side of the driveway that washed out. Put new fill in and spread rock over the new dirt.
Barn swallows have found our basement and started a family there. We get to watch baby barn swallows learn to fly. Then we put basement windows in. We don't want any more swallows. They are dirty.


Mid-July
We finally get our siding. We are working with a siding contractor who is willing to sell us siding and loan us a break. He pointed out that it costs more to finish a DIY job than to do it all himself. He thinks we won't finish it. HAH!!
9 weeks later
We finally finish the siding. We were determined to do this thing ourselves, but siding sure cost us a lot of time.
Sept, Oct, Nov
Now that the building is weatherproof, we can begin the electrical and plumbing work in earnest. Since Stan convinced the building officials that he could do those, we will get to DIY it on those projects.
Plumbing is a nuisance. The codes state that plumbing must handle an 8-foot water column or 35(?)psi air pressure. We started with the water test, but we had to haul all the water and put it in upstairs. It was pretty messy when a joint failed, too, so we bought temporary plugs for all the venting and outlets and air pressure tested it. When the inspector checked it out, he was surprised to see that we had followed the UPC as tightly as we had.

In the meantime, we plumbed the gas connection and got the propane tank in and the furnace installed. There was no provision to let a homeowner install HVAC. Too bad, too, because the contractor was a big disappointment. The weather was getting cold and all we lacked for heat in the house was the electricity.
The conduit for the electrical connection was laid in early November in the season's first snowstorm.

What was the nuisance was getting our water line. When the property was platted, the local utility okayed our lines running up the back of the property from a 12-inch main out on the main road. They changed their story in June and tried to make us put in a water main on our side street. We could not imagine how we could pay for a $44,000.00 water line for the neighborhood, even if we could get neighbors mistrustful of each other to cooperate. It was a long and political battle with repeated conferences with neighbors and the utility and exploring every possibility (including drilling a well)we could think of.


December 3
Stan went to the public meeting with BPU and presented our several months of efforts and they approved the arrangement they had originally agreed to. We will lay 1000 feet of water line down to the main road and tap the 12-inch main. WE HAVE WATER!!
We are the rest of the month digging trenches, getting meters and laying pipe. Now what is left is finishing.
End of December, first of January
Lots of friends rallied round to hang drywall. Even so, it took most of the month. Our next disappointment with the contractor who we paid to tape the joints and finish ceilings. He was only giving us scraps of time left over from other projects, and what was quoted to us a two-week job spread out over two months. In the end, Mom and I taped the garage and deducted it from his bill. It was good practice for later. I didn't intend to pay someone else to tape any more walls in our house.
February and March
As the drywall gets finished in rooms, we work on cabinetry so we can install plumbing fixtures. We have already decided to move in as soon as we can get our final inspection passed. It won't be finished, but it will be easier to work when we don't have to do all the driving from our old place. Many lights go in as cheap basic fixtures, just to get something attached to the wires. Upstairs will still be roughed in, no more, but we have two bedrooms and a bath on the main floor. It is enough.
April 8, 1987
The big day -- our final inspection. When the car drives up, I see the inspector who has been roughest on us. He is bringing someone with him. As they come in, He tells the other man "I want you to see this. They did it themselves." Wow. All the way through, he is bragging to his companion. As they finish, he tells me," I see something you need to change, but I will pass you anyway." and then proceeded to tell me how well he thought we had done. We needed to close off a PVC vent pipe that went up through the garage, no big deal. I was ecstatic. All this time I had been so nervous thinking that this guy had something against us.
We laid hardwood floor after that. Couldn't move piano in onto unfinished floor. Carpet could(and did) wait.

June 1987
Our official move-in was mid-month. Pets, plants, junk and furniture. Now we can get to all the oak finish work. No cabinet fronts or window trim yet. Walls are painted, but the ones which will get wallpaper are still waiting. Stan and I are sleeping in the future "library," and David and Anna are in the "guest room." We have a "two-year plan" and a "five-year plan" for when we will add certain features which we designed for but didn't want to spend money on yet. Someday, the library will get built in and someday the house will have proper porches and a sunroom. We will be replacing our hollow-core doors with ones we will build (we hope) and I am going to learn to make stained glass windows, because there are a couple of places which need lovely glass.

Home | Preparation | Photo gallery | Epilogue | Contact me

Site last updated May, 1999
Grace Troeh, grace@forthrt.com